What's changing2/5
- Virginia regulators (the SCC) created a new rate class, GS-5, for customers that use 25 megawatts or more. That's mostly data centers.
- It starts Jan. 1, 2027.
- These customers must pay for at least 85% of the transmission and distribution capacity they reserve, and 60% of generation, even if they use less.
- The goal, in the SCC's words: make sure data centers pay their own costs.
Your Dominion bill3/5
| Year | Typical home, per month |
|---|---|
| 2026 | +$11.24 |
| 2027 | +$2.36 |
From the SCC's Nov. 2025 rate decision. Both increases were well below what Dominion asked for: 23.7% lower in 2026, 51.2% lower in 2027.
Why it matters4/5
- Northern Virginia has the world's largest concentration of data centers, and they need huge amounts of power.
- Building that power and the lines to carry it costs money. The question is who pays: the data centers, or every household.
- The new rules shift more of that risk to the biggest users. Whether it goes far enough is still debated.
Struggling with your bill? Ask Dominion about payment plans, and check Virginia's energy assistance programs at dss.virginia.gov.
SOURCES · 5/5
Virginia State Corporation Commission: "SCC Issues Order on DEV Biennial Review," Case PUR-2025-00058, Nov. 25, 2025scc.virginia.govVirginia SCC: "SCC Data Center Initiatives: Ensuring Data Centers Pay Their Own Costs" fact sheet, Feb. 2026
Spot an error? Report a correction →
Get Mid-Atlantic money news every night
Taxes, wages, gov jobs and new laws, explained in a quick swipe. Sources on every post.
Follow @newsspool on Instagram